Puffin crossing delayed

Bellway Grange Liaison Committee have advised us of the following:

The start of the puffin crossing has now been delayed by approximately 12 weeks and currently has not start date.

Bellway will start removing spoil from site on 19th June which will take approximately 2 – 3 weeks.

There is also a National Grid upgrade to infrastructure happening at the bottom end of the village on Tuesday 17th between 9am & 3pm. It will affect all of Lakeside, Sandyfields and possibly properties up to the petrol station. It will include the butchers and Plants have decided to close on Tuesday 17th. The liaison committee are unsure regarding traffic management.